Build a costed, timed capital plan; do not assume a reserve percentage will cover known works. Separate recurring replacements, deferred maintenance, brand-mandated improvements and discretionary repositioning.

HVS’s 2026 development-cost survey is based on actual project budgets and provides broad development context. It is not a substitute for a property-specific renovation estimate, especially where an existing building’s condition and scope drive the work. (hvs.com)

Our recommended capital schedule includes:

Capital bucket Items to investigate
Building and infrastructure Roof, envelope, HVAC, plumbing, electrical and life safety
Guest product Rooms, bathrooms, corridors and public areas
Operating equipment Kitchen, laundry, technology and back-of-house systems
Compliance and brand requirements Costed obligations, approvals and deadlines
Project delivery Design, consultants, permits, freight, storage and project management
Trading disruption Room outages, outlet closures, retained staffing and reopening
Funding Interest, contingency, reserve availability and additional equity

A seller’s statement that a property has been renovated should be reconciled to invoices, completed scope and remaining requirements. HVS’s transaction guidance specifically identifies PIPs and deferred maintenance as issues to surface early. (publications.hvs.com)

Avoid double counting: track the reserve account separately. A transfer into that account and a later payment from it should not both reduce consolidated owner cash as though they were unrelated expenditures.